Conveying, Heap Leach, Waste Stacking Project at Russian gold mine

The harsh and remote conditions of a Russian gold mine posed a unique challenge for TNT, who were tasked with designing and supplying a complete conveying, heap leach and waste stacking project. The project was specifically designed to operate in extreme Arctic temperatures of up to -55°C, with a capacity of 2,000mtph. To ensure a seamless and efficient operation, TNT opted for a solution that included the use of modular electrical substations and E-rooms, while modularization and offsite pre-assembly enabled a faster and more cost-effective construction methodology.

SCOPE OF WORKS

  • Design Supply
    • Overland Stacking and Reclaim Conveyor System
    • By-Pass Fixed Stacker, Reclaim System
    • On-Off Heap Leach Mobile Stacking Reclaim System
    • Waste Ore Mobile Stacking System
  • Electrical Substations and Modular E-Rooms

DESIGN BASIS

  • Site Elevation: 1,400m
  • Material: Gold Ore, Waste
  • Capacity (design): 2,000mtph
  • Lump Size: 200mm
  • Temperature: -55°C min — 35°C max
  • Connected Power: 6,576 kw (winter)
  • System Operation: 4,233 kw (winter)

HIGHLIGHTS

  • Designed for –55°C “arctic duty” operation
  • Remote mine location
  • Modularization and offsite pre-assembly