Crushing and In-Plant Conveying project for copper mine in Chile

TNT partnered with Vial y Vives DSD for an Engineering, Procurement and Construction (EPC) project which involved the design and construction of a complete crushing and in-plant conveying system for a copper mine in Chile. The project was designed to handle copper material with a large capacity of 6,250mtph. TNT’s solution utilized Smartplant, as well as mixed onshore/offshore steel fabrication, modularization and offsite assembly techniques to ensure efficient project execution.

SCOPE OF WORKS

  • Engineering, Procurement and Construction (EPC) of the following:
    • Primary Crushing Facility
    • Primary Gyratory Crusher Station
    • Sacrificial Conveyor
    • Overland Conveying Facility
    • Overland Stacking Conveyor
  • Electrical Substations, Modular E-Rooms and Automation

DESIGN BASIS

  • Site Elevation: 1,700 m
  • Material: Copper
  • Capacity (design): 6,250 mtph
  • Lump Size: 305 mm
  • Temperature: 0°C to 35°C
  • Total Connected Power: 5,223 kW
  • System Operating Power: 3,101 kW

HIGHLIGHTS

  • Joint Venture w/ Vial y Vives DSD
  • Mixed onshore/offshore steel fabrication
  • Modularization and offsite assembly
  • Smartplant® Implementation