Heap Leach Stacking and Agglomeration Project in Burkina Faso

Heap Leach Stacking and Agglomeration Project in Burkina Faso

Heap Leach Stacking and Agglomeration Project in Burkina Faso
Agglomeration DrumsHeap Leach Systems

Location

Burkina Faso, Africa

Year

2016, 2018

Material

Gold

Application

Heap Leach Stacking

Heap Leach Stacking and Agglomeration Project for gold mine in Burkina Faso

A major gold operation in Burkina Faso required a heap leach stacking system that could handle operating in challenging conditions, including temperatures of up to 50°C. TNT designed and supplied an innovative solution, which required expansion two years after its original commissioning. The result was a highly efficient system capable of processing 7.5 million tonnes of ore per year and designed for 4-6 stacking lifts.

SCOPE OF WORKS

  • Design Supply, Technical Advisory Services
  • Agglomeration Drum, Overland Tripper Conveyor with Mobile Tripper feeding a Mobile Grasshopper Conveyor System with Telescoping Radial Stacker
  • Electrical, transformers, distribution ERooms
  • Overland Expansion, 2018

DESIGN BASIS

  • Site Elevation: 335m
  • Material: Gold
  • Capacity (design): 1707mtph
  • Lump Size: 32mm
  • Temperature: 16°C min — 50°C max
  • Connected Power: 2215kw
  • System Operation: 1694kw

HIGHLIGHTS

  • Extreme 50°C operating temperature
  • 7.5 mtpa of ore
  • 14 m long agglomeration drum
  • Designed for 4-6 stacking lifts